How long it takes to frame a house

A 2,000 square foot single-story house takes a framing crew about two to three weeks to frame and dry in. Two stories runs three to four. An addition is one to two weeks, a detached garage three to five days, and a basement is often a single long day.

  • Fully insured
  • SAM.gov registered
  • Firm quote within 24 hours of plans
  • Last updated: September 2026

Those are working days with a crew on site, not calendar time from contract to completion.

Typical framing durations

ProjectCrew daysCalendar, weather allowed
House, 1 story, 2,000 SF10 to 152 to 3 weeks
House, 2 story, 2,500 SF15 to 203 to 4 weeks
Addition, 400 SF5 to 101 to 2 weeks
Garage, 2 car detached3 to 5About 1 week
Basement framing, 200 LF1 to 21 to 3 days
Wall removal with beam1 to 3Within a week

A 200 linear foot basement of perimeter and partition walls is realistically one day: 200 linear feet of wall, three framers, one ten hour day.

What makes framing take longer

Roof complexity. The biggest factor by a distance. A simple gable roof goes on fast. Hips, valleys, dormers and multiple ridge heights can add a week to an otherwise ordinary house. Two houses of identical square footage can differ by 40 percent in framing time because of the roof alone.

Weather. Michigan. Rain stops sheathing and makes decks unsafe. Wind stops wall raising and truss setting outright, and that is a safety decision, not a preference. Winter shortens the usable day at both ends.

Material arriving wrong or late. The most common cause of a stalled frame, and it is a procurement problem, not a crew problem. A short order on trusses can idle a crew for days. On labor-only jobs this sits with the builder, which is why Mavericks sends the list of what to order.

Site access. If a delivery truck and a telehandler can reach the building, everything moves. A tight lot or a long carry adds hours to every single delivery.

Engineered members. LVL and steel beams and columns need planning, equipment and sometimes a second crew. A steel beam is its own day.

Plan revisions mid-build. A change after walls are up is not an edit, it is demolition and rebuild.

Inspection timing. The framing inspection is scheduled by the contractor of record. How fast the municipality shows up is outside anyone's control on site.

What does not make it faster

Adding people past a point. Framing has a critical path. Walls go up before the roof. Six people on a job sized for three mostly get in each other's way.

Skipping the layout. Time spent on accurate layout is recovered several times over. A frame that is out of square costs every trade behind it.

Pushing through bad weather. Wet lumber, unsafe decks and tired crews produce work that gets fixed later.

How Mavericks schedules

Start dates are committed in writing. Not "sometime in October."

Mavericks runs a crew of framers plus a second crew available for additional projects, so a schedule commitment does not depend on one job finishing exactly on time.

If something is going to move, you hear it from us first. The worst version of a delay is the one the builder discovers by driving out to an empty site.

Frequently asked questions

How long does it take to frame a 2,000 square foot house?

Framing a 2,000 square foot house takes about 10 to 15 crew days, or two to three weeks of calendar time with normal weather. A single story with a simple roof lands at the short end. A complex roof with hips and dormers pushes toward the long end or past it.

How long does it take to frame a two story house?

Framing a two story house of 2,500 square feet takes roughly 15 to 20 crew days, or three to four weeks. The second floor system and the extra wall height add time beyond the square footage difference alone.

How long does basement framing take?

Basement framing usually takes one day. The reference job for perimeter and partition walls: 200 linear feet of wall, three framers, one ten hour day. Add a day for soffits, bulkheads and bathroom rough framing.

What delays framing the most?

Framing is delayed most by material arriving late or short, and by roof complexity. Weather is third. Of the three, material is the most preventable, which is why the order list matters.

Can framing be done in Michigan winter?

Yes. Framing continues through winter. Days are shorter and high wind stops wall raising and truss setting for safety, so schedules carry more float from December through February.

When does the framing inspection happen?

The framing inspection happens after framing is complete and usually after mechanical rough-in, depending on the municipality. The contractor of record schedules it. Timing of the inspector's visit is not something the framing crew controls.